│ TUTORIAL: Work breakdown and PERT │
└────────────────────────────────────────────────┘
In this lesson you:
■ create a basic ~outline~2, called the Work
breakdown outline, for your project
■ create a basic ~structure~2, called the Work
breakdown structure, for your project
■ see how Harvard Project Manager 3.0
converts the Work breakdown information
to a PERT chart
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
HPM 3.0 offers a number of different ways
to create and manage projects. One common
method is called the Work breakdown. You
break a project down into its parts.
Planning for the Expo involves three major
parts, each made up of several tasks:
■ Booth -- plan, build, pack, ship, and
set up
■ Staff -- recruit and train
■ Materials -- order, pack, and ship
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1218
From the Main Menu, you select ~Create a project~2.
───────────────────────────────────────────────────
Type ~1~2><CMD>
<XFLD>1<XFLD><ENDDEF><F2><1><CMD><*1413
HPM 3.0 presents its default project creation
window, Fast track. You pull down the Data menu
to switch to the Work breakdown outline.
──────────────────────────────────────────────────
Press F3><CMD>
<XFLD><F3><XFLD><ENDDEF><CMD><*1813
Select ~Work breakdown outline~2.
──────────────────────────────────
Type ~4~2><CMD>
<XFLD>4<XFLD><CMD><*1413
The window appears with the first blank ready to
accept your first task.
─────────────────────────────────────────────────
Type ~Booth~2><CMD>
<XFLD>Booth<XFLD><ENDDEF><CMD><*1313
For now, ignore the other columns. You can enter
a task with F10, Arrow keys, or Enter.
─────────────────────────────────────────────────
Press Down Arrow><CMD>
<XFLD><DN><XFLD><ENDDEF><CMD><*1316
Since this is the first task, HPM wants to know
how to treat tasks on that level--as either
parallel or sequential tasks.
─────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1316
Booth occurs at the same time as Materials and
Staff (to be entered later). Confirm the default.
──────────────────────────────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*1314
HPM automatically displays another blank line. You
can move the blank before you start typing. You
want to indent it one space to the right.
──────────────────────────────────────────────────
Press Right Arrow><CMD>
<XFLD><RGT><XFLD><ENDDEF><CMD><*1313
The Booth task includes planning and building. You
name this task Plan. Once you start typing, the
field changes and can't be moved. To move it, you
have to choose Move task (covered later).
───────────────────────────────────────────────────
Type ~Plan~2><CMD>
<XFLD>Plan<XFLD><ENDDEF><CMD><*1314
This task is going to last a week, or five
working days. Now move the cursor to the
Planned Duration column.
──────────────────────────────────────────
Press Tab twice><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*1314
Now type in the number of working days.
───────────────────────────────────────
Type ~5~2><CMD>
<XFLD>5<XFLD><ENDDEF><CMD><*1314
Move to the Responsible column.
─────────────────────────────────────
Press Tab twice again><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*1314
You're the one responsible.
You oversee the work of a
resource. (Assigning tasks
to resources comes later.)
───────────────────────────
Type ~SalesMgr~2><CMD>
<XFLD>SalesMgr<XFLD><ENDDEF><CMD><*0410
Now move back to
the Name column.
────────────────────
Press Shift-Tab
four times><CMD>
<XFLD><STAB><STAB><STAB><STAB><XFLD><ENDDEF><CMD><*1416
You can now enter this
information.
─────────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><ENDDEF><CMD><*1416
Since this is another new level, HPM again asks
about the tasks. On this level they occur in
sequence, with planning before building.
──────────────────────────────────────────────────
Press Right Arrow><CMD>
<XFLD><RGT><XFLD><ENDDEF><CMD><*1416
Confirm your selection.
─────────────────────────────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*2016
Add the Build task at this level.
──────────────────────────────────
Type ~Build~2><CMD>
<XFLD>Build<XFLD><ENDDEF><CMD><*2016
Move to the Planned
Duration column.
──────────────────────
Press Tab twice><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*2016
You estimate 10 days.
──────────────────────
Type ~10.0~2><CMD>
<XFLD>10.0<XFLD><ENDDEF><CMD><*2016
Move to ~Responsible~2.
───────────────────────
Press Tab twice><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*0412
The Maintenance Manager
is responsible.
───────────────────────
Type ~MaintMgr~2><CMD>
<XFLD>MaintMgr<XFLD><ENDDEF><CMD><*0410
Move back to
the Name column
in one jump.
────────────────────
Press the Home key><CMD>
<XFLD><HOME><XFLD><ENDDEF><CMD><*0410
You can now enter
this information.
─────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><ENDDEF><CMD><*0410
Since you won't add
more tasks now, you
back out.
────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><ENDDEF><CMD><*1413
That's enough for the outline. You now
switch to the Work breakdown structure.
Start by pulling down the Graphs menu.
───────────────────────────────────────────
Press F2><CMD>
<XFLD><F2><XFLD><ENDDEF><CMD><*1415
Select ~Work breakdown~2.
──────────────────────────
Type ~4~2><CMD>
<XFLD>4<XFLD><CMD><*4008
This is the Work breakdown
structure window. The box
at the top represents the
~Goal~2 of your project, the
HiTech Expo. It already
has converted the tasks you
entered in the outline.
────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*4012
The triangular cursor should
be in the ~Goal~2 box to add
a task at the same level as
Booth. We want to add Staff
next -- at that level.
────────────────────────────
Press Up Arrow twice><CMD>
<XFLD><UP><UP><XFLD><ENDDEF><CMD><*4012
Now you can add a new task.
Start by pulling down the
Edit menu.
───────────────────────────
Press F4><CMD>
<XFLD><F4><XFLD><ENDDEF><CMD><*4012
The Edit menu lists the
features you use to add
and change tasks in a
Work breakdown structure.
Select ~Add task~2.
──────────────────────────
Type ~2~2><CMD>
<XFLD>2<XFLD><CMD><*4002
The fill-in shows the new task
goes under ~Goal~2. That's
right where you want it.
──────────────────────────────
Type ~Staff~2><CMD>
<XFLD>Staff<XFLD><ENDDEF><CMD><*4003
Next, you indicate the person
responsible for the task.
─────────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*4003
The Training Manager is
the one responsible.
────────────────────────
Type ~TrainMgr~2><CMD>
<XFLD>TrainMgr<XFLD><ENDDEF><CMD><*4003
The fill-in
is complete.
──────────────
Press F10><CMD>
<XFLD><F10><XFLD><CMD><*1814
HPM adds the Staff task to the Work breakdown
structure, just below ~Goal~2 -- at the same
level as Booth. Later you can add subtasks
(recruiting and training) below Staff.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*0516
Use the Add task speed key.
───────────────────────────
Press Ctrl-A><CMD>
<XFLD><CtrlA><XFLD><ENDDEF><CMD><*0516
Add the Materials task.
───────────────────────────
Type ~Materials~2><CMD>
<XFLD>Materials<XFLD><ENDDEF><CMD><*0515
Move the cursor to the
~Responsible~2 field.
─────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*0515
The Production Manager is
responsible.
─────────────────────────
Type ~ProdMgr~2><CMD>
<XFLD>ProdMgr<XFLD><ENDDEF><CMD><*0516
The fill-in is complete.
─────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*1515
HPM adds the new task at the same level as
Staff and Booth.
────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1515
Now add tasks below Staff, at the third level of
structure -- or, the Plan and Build level.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*0615
Use the Add task speed key.
───────────────────────────
Press Ctrl-A><CMD>
<XFLD><CtrlA><XFLD><ENDDEF><CMD><*0615
Move the cursor to the
~Below task~2 field.
──────────────────────────
Press Up Arrow><CMD>
<XFLD><UP><XFLD><ENDDEF><CMD><*0613
When the cursor is in the
~Below task~2 field, you
can move the triangular
cursor in the window.
──────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*0611
Now, each time you press
a cursor movement key,
HPM moves the triangular
cursor. Move the cursor
so that the ~Below task~2
field changes to ~Staff~2.
──────────────────────────
Press Down Arrow><CMD>
<XFLD><DN><XFLD><ENDDEF><CMD><*0613
The ~Below task~2 field
shows the name of the task
you want. Now move back
to the ~Name~2 field.
──────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*0615
Type a name for the new
task.
──────────────────────────
Type ~Recruit~2><CMD>
<XFLD>Recruit<XFLD><ENDDEF><CMD><*0615
Move the cursor to the
~Responsible~2 field.
──────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*0415
The Training Manager is
responsible for recruiting.
───────────────────────────
Type ~TrainMgr~2><CMD>
<XFLD>TrainMgr<XFLD><ENDDEF><CMD><*0616
The fill-in is complete.
────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*1317
Tasks at this new level will be done in sequence.
──────────────────────────────────────────────────
Press the Right Arrow key and then F10><CMD>
<XFLD><RGT><F10><XFLD><ENDDEF><CMD><*0615
Add one more task at this
level.
──────────────────────────
Press Ctrl-A><CMD>
<XFLD><CtrlA><XFLD><ENDDEF><CMD><*0615
Add a task for training
the booth sales staff.
──────────────────────────
Type ~Train~2 and press Tab><CMD>
<XFLD>Train<TAB><XFLD><ENDDEF><CMD><*0615
The Training Manager is
also responsible here.
─────────────────────────
Type ~TrainMgr~2><CMD>
<XFLD>TrainMgr<XFLD><ENDDEF><CMD><*0616
The fill-in is complete.
─────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><CMD><*1415
You would normally continue adding tasks, but now
you can see how HPM converts these tasks to a
PERT chart. Start by pulling down the Graphs menu.
──────────────────────────────────────────────────
Press F2><CMD>
<XFLD><F2><XFLD><ENDDEF><CMD><*1216
Select ~PERT chart~2.
─────────────────────
Type ~2~2><CMD>
<XFLD>2<XFLD><CHOME><CMD><*1416
The PERT chart is the heart of any project plan. It shows
tasks arranged in a network of relationships.
───────────────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
You can't see the whole PERT chart, but all your tasks
have been converted, as you will see in a moment.
─────────────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
The first box in the PERT chart, ~Start~2, is a milestone.
─────────────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
Milestones mark the start and end of a series of tasks.
They can also act as checkpoints for important events in
a project. You'll learn more about milestones in Lesson 5.
──────────────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
All PERT charts include Start and End milestones. The
~End~2 milestone for this project is off the screen.
Move the cursor to the end of the PERT chart to view it.
────────────────────────────────────────────────────────
Press the End key><CMD>
<XFLD><END><XFLD><ENDDEF><CMD><*1416
Now move the cursor left on the PERT chart.
──────────────────────────────────────────────────
Press the Left Arrow key four times><CMD>
<XFLD><LFT><LFT><LFT><LFT><XFLD><ENDDEF><CMD><*1416
The screen changes. Shift one more position left.
──────────────────────────────────────────────────
Press the Left Arrow key once more><CMD>
<XFLD><LFT><XFLD><ENDDEF><CMD><*1416
Notice how HPM displays ~Booth~2 and ~Staff~2. They
occur at the same time, so HPM displays them on
parallel paths in the PERT chart.
───────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
The lowest level tasks (~Plan~2 and ~Build~2 under
Booth, and ~Recruit~2 and ~Train~2 under Staff) are
shown in sequence --just as they occur.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
The milestones ~Booth~2 and ~Staff~2 precede their
tasks; and the milestones ~Booth End~2 and ~Staff~2
~End~2 follow them.
─────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
You learn more about the PERT chart in later
lessons. That's all for this one.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1416
You return to the Main Menu by backing out...
─────────────────────────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CMD><*1416
One more time...
───────────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CMD><*1204
~In summary ...~2
■ Select ~Create a project~2 at the Main
Menu to begin a new project.
■ Start your project in the ~Work breakdown~2
~outline~2 window
■ Use the ~Work breakdown structure~2 for a
still another view of your project.
■ HPM can create a detailed ~PERT chart~2 from
your Work breakdown data.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF>